From YouTube: East Biloxi infrastructure update, Nov. 8, 2016
Description
Project superintendent John Cowart with Oscar Renda Contracting, the firm rebuilding and replacing infrastructure covering 55 miles of streets north of the CSX railway in east Biloxi, provided this update on the project.
A
A
Right
now
we
are
working
to
complete
the
drainage
structures
on
Holly,
Street,
north
and
south
of
division,
with
hopes
of
paving
going
down
before
Christmas,
also
we're
working
on
completing
the
drainage
structures
on
Penny
Avenue,
with
hopes
of
paving
going
down
on
this
street
before
Christmas
only
street
north
of
the
division.
We
are
currently
working
to
complete
the
gravity
sewer
system.
This
work
should
be
complete
by
the
first
of
December,
once
the
sewer
is
complete
on
Lee
Street
north
of
division.
A
This
will
allow
us
to
activate
the
sewer
system
on
Keller,
Bowen
and
Holly,
making
this
another
large
area
that
we
anticipate
on
paving
the
beginning
of
next
year
on
the
west
end
of
the
project,
we're
installing
the
deed
gravity,
sewer
main
on
Division
Street
between
Santini
and
bone
street.
We
plan
on
this
work
being
completed
by
the
end
of
the
year,
which
will
allow
us
to
continue
each
towards
Calvet.
A
Also,
on
Thelma
Street
were
working
to
complete
both
the
sewer
and
storm
drain,
making
Thelma
and
saliva
new
south
of
the
division,
the
next
two
streets
that
were
see
paving
between
Hopkins
and
ground,
south
of
division,
we're
currently
working
to
both
pressure
test
and
chlorinate.
The
new
water
main,
which
will
allow
us
to
terminate
the
old.
So
residents
may
experience
some
short-term
outages
again.
We
thank
the
residents
of
Biloxi
for
their
patience.