From YouTube: East Biloxi Infrastructure Update, May 29, 2019
Description
Here are east Biloxi infrastructure updates from Oscar Renda Contracting and Hemphill Construction Co. Oscar Renda is the firm rebuilding and replacing infrastructure covering 55 miles of streets north of the CSX railway in east Biloxi. Hemphill is rebuilding infrastructure on eight miles of roadways south of the CSX Railway, from downtown to Seashore Methodist. To see detailed maps showing progress on installing water mains, sewer, drainage and paving for north and south of the CSX railway, visit https://biloxi.ms.us/restore-biloxi/
A
We
are
in
the
corner
of
strawberry,
completing
the
drainage
structures,
the
drainage
pipe
has
been
completed.
We
have
moved
on
to
Walker
and
elder
streets
to
begin
installing
the
massive
amount
of
storm
drain
pipe
and
structures
that
was
added
due
to
engineering
design
errors.
Our
crews
will
be
following
right
behind
with
drainage
structures
on
Walker
and
Elder
base
course
of
asphalt
has
been
completed
on
Main,
Street,
south
of
division,
and
we
are
about
75%
complete
with
the
driveways
and
sidewalks.
We
will
be
following
behind
immediately
with
landscaping.
A
We
continue
moving
west
with
prepping
the
streets
and
install
in
the
final
course
of
asphalt.
We've
installed
the
final
course
of
asphalt
on
Division
Street
from
oak
to
Lee,
Garrick,
wink,
Murray
and
fallow
streets,
fountain
brown
and
Holly
streets.
By
the
end
of
this
month,
we
will
have
the
final
course
of
asphalt
on
esters
from
Holly
to
Lee,
on
Keller,
Austin,
Suarez,
Heidenheim
and
part
of
Lee
Street,
north
of
division
and
possibly
some
additional
streets
west
of
league.
We
are
continuing
to
install
sewer
on
forest.
A
The
work
is
deep
and
a
lot
of
more
water
than
we
anticipated
making
it
quite
challenging.
We
have
completed
the
storm
drain,
work
on
cruces
and
have
begun
installing
the
road
base.
We
anticipate
installing
base
course
of
asphalt
by
the
end
of
this
month
as
well.
We
have
installed
base
quarts
of
asphalt
on
bone,
Street
and
angle
otta
south
of
elder.
We
are
installing
fences
throughout
the
project,
along
with
continued
road
maintenance
and
landscaping.
B
B
Hi,
my
name
is
Jack
gråvik
I'm,
the
assistant
project
manager
for
Hemphill
construction
on
the
Biloxi
South
contract
and
I'm.
Here,
to
give
you
an
update
on
the
progress
of
our
work,
we
currently
have
two
crews
working
on
the
storm
drainage
on
st.
Francis
Street,
along
with
the
subcontractor
working
on
pouring
concrete.
We
have
a
sewer
crew
working
on
Bonacci,
Avenue
they'll,
hopefully
be
complete
with
that
sewer
installation.
B
In
a
couple
weeks,
we
also
have
two
other
crews,
one
working
on
White
Avenue
on
the
water
line,
installation
and
another
working
on
father
Ron
at
the
corner
of
Morrison
Avenue
working
on
the
sewer
installation.
As
you
can
see
here,
we
have
just
completed
pavement
on
father,
run
from
Keesler
circle
to
st.
Francis
Street.
We
also
just
completed
pavement
on
guild
Avenue
and
Irish
Hill
from
Porter
to
Gill
Avenue.
B
The
pavement
that
was
put
down
on
Hopkins
Boulevard
is
temporary
and
will
be
removed
for
a
couple
weeks
to
finish
the
construction
and
then,
after
that,
permanent
base
asphalt
will
be
put
down.
And
finally,
we
have
a
road
crew.
Putting
the
rock
base
on
a
zillya
drive
to
get
that
ready
for
base
asphalt,
they'll
be
working
on
multiple
other
streets
throughout
the
next
couple
months,
getting
ready
for
base
asphalt.
We
would
like
to
thank
everybody
again
for
driving
safe
around
our
construction
zones
and
keeping
our
employees
safety
in
mind
at
all
times.
Thank
you.