From YouTube: East Biloxi infrastructure update, Feb. 25, 2019
Description
Here are east Biloxi infrastructure updates from Oscar Renda Contracting and Hemphill Construction Co. Oscar Renda is the firm rebuilding and replacing infrastructure covering 55 miles of streets north of the CSX railway in east Biloxi. Hemphill is rebuilding infrastructure on eight miles of roadways south of the CSX Railway, from downtown to Seashore Methodist. To see the detailed project maps as of Feb. 13, 2019, visit www.biloxi.ms.us/wp-content/uploads/2019/02/ProjectMaps02192019.pdf
A
Hi
I'm
Jennifer
Matranga
at
the
project
manager
for
Oskar
into
contracting
I'm
here
to
give
a
progress,
update
on
the
status
of
the
infrastructure
project
north
of
the
tracks.
Right
now
we
are
on
Main
Street,
which
we
just
paved
the
base
course
of
asphalt
north
of
Division.
We
are
currently
putting
in
sidewalks
and
then
you
could
see
south
of
division,
we're
putting
in
storm
drainage
and
sewer
and
storm
drain
structures
north
on
Main
Street.
A
We
have
paved
all
the
way
to
Bradford
and
we
have
installed
the
road
base
from
Bradford
to
elder
and
we'll
be
installing
the
curbing
today
in
tomorrow,
and
installing
base
course
of
asphalt
towards
the
end
of
the
week
on
the
east
end
of
the
project,
we're
continuing
to
install
surface
course
of
asphalt
most
recently.
Last
week
we
installed
all
the
surface
course
of
asphalt
on
Crawford
Street
from
old,
Back
Bay.
A
We
will
continue
installing
surface
course
on
stron
G,
north
of
division,
Sam,
Street
and
Penny
Lane,
followed
by
fountain
Keller
Austin
Brown
Bowen,
which
we
are
methodically
working
our
way
west
of
the
project
with
surface
course.
We
should
be
installing
the
remainder
of
the
street
signs
and
striping
on
the
east
end
of
the
project
on
all
streets,
east
of
Oak
Street
within
the
next
month.
We've
installed
all
the
sidewalks
on
Bradford
and
ylim
use
and
are
going
right
behind
that
with
restoration
work
base
course
of
asphalt
will
be
going
down
on
Cruces.
A
Shortly
following
that
it'll
be
Magnolia,
Street
will
beginning
base
course
of
asphalt.
We
have
crews
on
own
street
installing
the
storm
drain
structures.
Once
those
structures
are
complete,
which
will
be
at
the
beginning
of
next
month,
then
the
the
road
base
crew
will
get
in
there
installing
the
road
base,
then
the
curbing
then
the
base
course
of
asphalt.
We
are
installing
sidewalks
on
cuarón's.
We
are
completing
the
road
base
on
Porter
after
Magnolia,
then
Porter
will
be
the
next
street
to
get
base
course
of
asphalt.
A
And
finally,
we
are
on
Bonacci
installing
the
last
of
the
utilities.
South
of
the
tracks
to
tie
in
the
water
south
of
the
tracks
to
north
of
the
tracks
we
have
the
sewer
tied
in,
and
that
is
complete
once
the
water
is
tied
in,
will
begin
finishing
up
the
storm
drain,
which
is
some
of
the
biggest
toughest
and
deepest
storm
drain
on
the
project.
A
B
Hi,
my
name
is
Jai
gråvik
I'm,
the
assistant
project
manager
for
Hill
Construction
on
the
Biloxi
South
contract
and
I'm.
Here,
to
give
you
an
update
on
the
progress
of
our
work
well,
you're
on
Porter
Avenue,
where
we
have
just
completed
putting
the
base
asphalt
down.
We've
also
completed
the
base
asphalt
on
Yonge
and
drop
lestrade
north
and
south
Bolton
lane
and
Roselle
Street.
We
currently
have
crews
working
on
Benecke,
Avenue,
Azalea,
Drive,
st.
Paul,
Street
and
multiple
other
concrete
crews
and
cleanup
crews
finishing
up
areas
around
the
project.
We
know.
B
One
of
the
main
concerns
on
the
Gulf
Coast
is
the
status
of
our
work.
During
Mardi
Gras,
we
will
have
the
entire
parade
route
open
and
paved
for
Mardi
Gras.
The
only
streets
that
will
be
closed
will
be
been
a
key
have
anew
in
Azalea
Drive.
We
will
not
have
crews
working
that
day
due
to
the
heavy
traffic,
but
those
two
streets
will
be
closed.
On
Urschel
drive
will
be
open
as
well
with
base
limestone
down.
We
also
have
dirt
crews,
putting
the
rock
down
on
Gill
Avenue,
Irish,
Hill,
Drive
and
father
rod
Avenue.
B
We
hope
by
next
month
have
base
asphalt
down
on
the
disturbed
area
as
a
father
on
st.
Paul
Street
south,
a
father
on
Gill
Avenue
and
Irish
he'll
drop,
one
of
our
biggest
obstacles
of
this
project
has
been
completing
Porter,
Avenue,
Howard,
Avenue
and
I
Rochelle
Duda.
As
you
can
see
the
heavy
traffic
on
these
streets.
We
know
it
wasn't
an
inconvenience
to
the
public,
but
we
appreciate
everyone's
cooperation
as
we
completed
this
work.