15 Mar 2022
This is the sync planning session for the 14.10 milestone for the Manage:Import group.
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17472
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17472
- 7 participants
- 39 minutes
7 Mar 2022
Haris Delalić from the Import Team reviews the current state of the Bitbucket Importer by doing a quick import from Bitbucket Cloud into GitLab.com.
Doc: https://docs.gitlab.com/ee/user/project/import/bitbucket.html
Doc: https://docs.gitlab.com/ee/user/project/import/bitbucket.html
- 1 participant
- 9 minutes
6 Mar 2022
Haris Delalić from the Import Team reviews the current state of the GitLab Migration feature to import a Group including Subgroups and Projects from one instance of GitLab to another.
Feedback issue: https://gitlab.com/gitlab-org/gitlab/-/issues/284495
Feedback issue: https://gitlab.com/gitlab-org/gitlab/-/issues/284495
- 2 participants
- 19 minutes
3 Mar 2022
GitLab team members are located in 68 countries! Let's learn some fun words in other languages and then contribute to GitLab localization!
We will start by sharing which country each person is from and what languages they speak and each person will teach the group some words (like hello, how are you? good morning, good evening).
After this introduction round, the presenter will show how to contribute to GitLab's localization. We will all pull out our laptops and contribute to additional language support for GitLab.
Link to presentation: https://docs.google.com/presentation/d/1WWOCPYmWut8wXJowBgQg2mTI6XdLFk3m7fAHO8X8AvU/edit#slide=id.g55e9452978_0_75
We will start by sharing which country each person is from and what languages they speak and each person will teach the group some words (like hello, how are you? good morning, good evening).
After this introduction round, the presenter will show how to contribute to GitLab's localization. We will all pull out our laptops and contribute to additional language support for GitLab.
Link to presentation: https://docs.google.com/presentation/d/1WWOCPYmWut8wXJowBgQg2mTI6XdLFk3m7fAHO8X8AvU/edit#slide=id.g55e9452978_0_75
- 2 participants
- 47 minutes
28 Feb 2022
Haris Delalić from the Import Team walks through another migration from GitHub into GitLab.
- 1 participant
- 14 minutes
11 Feb 2022
This is the sync planning session for the 14.9 milestone for the Manage:Import group.
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17460
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17460
- 4 participants
- 31 minutes
14 Jan 2022
This is the sync planning session for the 14.8 milestone for the Manage:Import group.
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17439
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17439
- 4 participants
- 30 minutes
15 Dec 2021
This is the sync planning session for the 14.7 milestone for the Manage:Import group.
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17429
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17429
- 4 participants
- 30 minutes
30 Nov 2021
Haris Delalić from the Import Team walks through import from FogBugz into GitLab.
- 2 participants
- 15 minutes
15 Nov 2021
This is the sync planning session for the 14.6 milestone for the Manage:Import group.
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17412
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17412
- 6 participants
- 30 minutes
14 Oct 2021
This is the sync planning session for the 14.5 milestone for the Manage:Import group.
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17397
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17397
- 3 participants
- 18 minutes
15 Sep 2021
This is the sync planning session for the 14.4 milestone for the Manage:Import group.
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17383
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17383
- 7 participants
- 45 minutes
28 Aug 2021
Haris Delalić from the Import Team test-drives the GitLab Migration feature to import a Group from one instance of GitLab to another.
Feedback issue: https://gitlab.com/gitlab-org/gitlab/-/issues/284495
Feedback issue: https://gitlab.com/gitlab-org/gitlab/-/issues/284495
- 1 participant
- 11 minutes
16 Aug 2021
Import 14.3 planning issue: https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17369
- 2 participants
- 4 minutes
12 Aug 2021
This is the sync planning session for the 14.3 milestone for the Manage:Import group.
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17369
Notable issue mentioned:
Migrate Empty Projects - https://gitlab.com/gitlab-org/gitlab/-/issues/267948
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17369
Notable issue mentioned:
Migrate Empty Projects - https://gitlab.com/gitlab-org/gitlab/-/issues/267948
- 4 participants
- 45 minutes
3 Aug 2021
Haris Delalić from the Import Team talks about the group's direction and roadmap.
Link: https://about.gitlab.com/direction/manage/importers/
Link: https://about.gitlab.com/direction/manage/importers/
- 1 participant
- 5 minutes
13 Jul 2021
This is the sync planning session for the 14.2 milestone for the Manage:Import group.
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17354
Notable epics mentioned:
Complete Epic migration - https://gitlab.com/groups/gitlab-org/-/epics/5189
Group Migration API - https://gitlab.com/gitlab-org/gitlab/-/issues/301109
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17354
Notable epics mentioned:
Complete Epic migration - https://gitlab.com/groups/gitlab-org/-/epics/5189
Group Migration API - https://gitlab.com/gitlab-org/gitlab/-/issues/301109
- 3 participants
- 15 minutes
16 Jun 2021
This is the sync planning session for the 14.1 milestone for the Manage:Import group.
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17339
Notable epics mentioned:
Complete Epic migration - https://gitlab.com/groups/gitlab-org/-/epics/5189
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17339
Notable epics mentioned:
Complete Epic migration - https://gitlab.com/groups/gitlab-org/-/epics/5189
- 4 participants
- 25 minutes
13 May 2021
This is the sync planning session for the 14.0 milestone for the Manage:Import group.
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17328
Notable epics mentioned:
Complete Epic migration - https://gitlab.com/groups/gitlab-org/-/epics/5189
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17328
Notable epics mentioned:
Complete Epic migration - https://gitlab.com/groups/gitlab-org/-/epics/5189
- 4 participants
- 27 minutes
13 Apr 2021
This is the sync planning session for the 13.12 milestone for the Manage:Import group.
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17325
Notable epics mentioned:
Complete Epic migration - https://gitlab.com/groups/gitlab-org/-/epics/5189
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17325
Notable epics mentioned:
Complete Epic migration - https://gitlab.com/groups/gitlab-org/-/epics/5189
- 5 participants
- 29 minutes
16 Mar 2021
This is the sync planning session for the 13.11 milestone for the Manage:Import group.
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17318
Notable epics mentioned:
Complete Epic migration - https://gitlab.com/groups/gitlab-org/-/epics/5189
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17318
Notable epics mentioned:
Complete Epic migration - https://gitlab.com/groups/gitlab-org/-/epics/5189
- 3 participants
- 22 minutes
26 Feb 2021
This is the sync planning session for the 13.10 milestone for the Manage:Import group.
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17311
Notable epics mentioned:
Complete Epic migration - https://gitlab.com/groups/gitlab-org/-/epics/5189
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17311
Notable epics mentioned:
Complete Epic migration - https://gitlab.com/groups/gitlab-org/-/epics/5189
- 4 participants
- 34 minutes
13 Jan 2021
This is the sync planning session for the 13.9 milestone for the Manage:Import group.
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17303
Notable epics mentioned:
Complete Epic migration - https://gitlab.com/groups/gitlab-org/-/epics/5189
Scaling the GitHub Importer - https://gitlab.com/groups/gitlab-org/-/epics/5042
Tech debt - https://gitlab.com/groups/gitlab-org/-/epics/4931
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17303
Notable epics mentioned:
Complete Epic migration - https://gitlab.com/groups/gitlab-org/-/epics/5189
Scaling the GitHub Importer - https://gitlab.com/groups/gitlab-org/-/epics/5042
Tech debt - https://gitlab.com/groups/gitlab-org/-/epics/4931
- 5 participants
- 43 minutes
11 Dec 2020
This is the sync planning session for the 13.8 milestone for the Manage:Import group.
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17299
Planning issue shown:
https://gitlab.com/gitlab-org/manage/general-discussion/-/issues/17299
- 6 participants
- 35 minutes
3 Dec 2020
Haris Delalić from the Import Team walks through migration from GitHub into GitLab.
- 1 participant
- 17 minutes
5 Sep 2020
Haris Delalić from the Import Team talks about the Vision and Goals for the Group:Import.
Link: https://about.gitlab.com/direction/manage/#import
Link: https://about.gitlab.com/direction/manage/#import
- 1 participant
- 2 minutes